Minimizing the duration of repetitive construction processes with work continuity constraints
Materiały konferencyjne
MNiSW
20
Lista 2021
Status: | |
Autorzy: | Jaśkowski Piotr, Biruk Sławomir |
Dyscypliny: | |
Aby zobaczyć szczegóły należy się zalogować. | |
Rok wydania: | 2019 |
Wersja dokumentu: | Elektroniczna |
Język: | angielski |
Wolumen/Tom: | 7 |
Numer artykułu: | 14 |
Strony: | 1 - 11 |
Web of Science® Times Cited: | 8 |
Scopus® Cytowania: | 11 |
Bazy: | Web of Science | Scopus | dblp Computer Science Bibliography (Universität Trier) | DOAJ | Genamics JournalSeek | Inspec |
Efekt badań statutowych | TAK |
Materiał konferencyjny: | TAK |
Nazwa konferencji: | 8th International Conference from Scientific Computing to Computational Engineering |
Skrócona nazwa konferencji: | IC-SCCE 2018 |
Termin konferencji: | 4 lipca 2018 do 7 lipca 2018 |
Miasto konferencji: | Ateny |
Państwo konferencji: | GRECJA |
Publikacja OA: | TAK |
Licencja: | |
Sposób udostępnienia: | Otwarte czasopismo |
Wersja tekstu: | Ostateczna wersja autorska |
Czas opublikowania: | W momencie opublikowania |
Data opublikowania w OA: | 6 marca 2019 |
Abstrakty: | angielski |
This study adopts the flow shop concept used in industrial production to schedule repetitive non-linear construction projects, where specialized groups of workers execute processes in work zones (buildings) in a predefined order common to all groups. This problem is characteristic of construction projects that involve erecting multiple buildings. As the duration of the project heavily depends upon the sequence of the work zones, this study aims at providing a model and a practical approach for finding the optimal solution that assures the shortest duration of the project, allows the contractor to complete particular work zones (buildings) as soon as possible (without idle time), and conforms to a predefined sequence of work zone completion. This last constraint may arise from the client’s requirements or physical conditions of the project and has not been addressed by existing scheduling methods. Reducing the duration of the entire project brings the benefit of lower indirect costs and, if accompanied by a reduced duration of completing particular buildings (i.e., work zones), may also provide the opportunity to sell project deliverables sooner, thus improving the economic efficiency of the project. In search of optimal schedules, the authors apply the algorithms of Minimum Hamiltonian Cycle/Asymmetric Traveling Salesman Problem (ATSP). |